Superior Clause in Contract Absolves Subcontractor

Building contracts often involve a multiplicity of documents, which sometimes have conflicting terms. In such cases, the liabilities under the contracts will depend on which of the various contractual terms has primacy over the others.

In a recent contractual dispute involving dredging and back-filling works, a clause that required a subcontractor to ‘check the design and accept responsibility’ for the works it carried out and to use ‘reasonable care and diligence’ in designing its works was deemed not to make the subcontractor liable when the works were found to need considerable rectification.

The reason for this was straightforward. The subcontractor’s tender document, which formed part of the bundle of contracts, contained a clause which rendered it ‘not responsible for the design of any of the …works’. This clause prevailed over the other clause and was sufficient to absolve the subcontractor from liability for the defective design of the works.

The contents of this article are intended for general information purposes only and shall not be deemed to be, or constitute legal advice. We cannot accept responsibility for any loss as a result of acts or omissions taken in respect of this article.

Ask a free legal question

Complete this simple form if you
would like to ask us a
free legal question
 

What Our Clients Say

We would like to thank you for the superb work and attention to detail that has gone into our dispute with the council so far! 

Our Architect put together a very professional document which was further enhanced and polished by your very professional input. 

You are in fact unique in my personal experience of the legal profession in that you take your duty of care very seriously. It is obvious that the outcome concerns you greatly and your determination to win is much appreciated!

Thank you from us both. 

Best Regards
 
Mr and Mrs X, Surrey